July 23, 2018

IFM REPLACES A BAR RACK WITH A GRINDER STATION TO MAINTAIN FLOW

Municipal Wastewater - In the summer of 2016, IFM was approached by an existing client to maintain sewage flow at a facility near Valparaiso, IN. This client has regular, high flow with a large amount of debris in it. This debris was plugging the...
July 23, 2018

IFM CREATES A CUSTOM RO DESIGN FOR AUTOMOTIVE PROCESS WATER

Industrial WTP - A Detroit, Michigan paint coating facility added another facility in Jeffersonville, Indiana. This company approached IFM to design and fabricate two complete water treatment systems for the facility coating and washing...
July 23, 2018

IFM AIDS IN WATER PURIFICATION FOR A HORSE FARM

Commercial Water Treatment System - In the fall of 2016, IFM was contacted by a competitive horse farm in Michigan to help with the treatment of their well water. The farm land was on an old salt mine, so the ground water had an extreme amount of salt...
August 8, 2018

IFM DESIGN/BUILDS AND OPERATES NEW NATIONAL TRAVEL CENTER WASTEWATER TREATMENT...

A National Travel Center contacted IFM regarding an existing wastewater treatment facility that needed some upgrades. The existing facility, rated for 20,000 gallons per day (GPD), was currently meeting limits but the plant was deteriorating. The plant was an...
November 2, 2018

IFM DESIGNS CUSTOM UF/ RO SYSTEM TO TREAT HIGH AMMONIA

Municipal Wastewater - IFM was contacted by a long-term client regarding a facility that was having compliance issues. They were particularly struggling with was their ammonia limit. The waste stream at this facility is primarily composed...
January 19, 2019

QUICK ACTION RESOLVES AN URGENT WASTEWATER ISSUE

IFM recently finished implementing a large-scale water system for an industrial client. Upon completion of the water system, this same client’s existing wastewater treatment system took a turn for the worse...
May 6, 2019
travel center water and wastewater system

IFM CONSTRUCTS A NEW WATER AND WASTEWATER SYSTEM FOR A NATIONAL TRAVEL CENTER...

A National Travel Center client solicited IFM to design, install, and operate both a water and wastewater system for its new facility in Florida (5,000-10,000 gallons per day)...
June 20, 2019

IFM UPGRADES A FAILING WATER SYSTEM FOR A NATIONAL TRAVEL CENTER

In July, IFM took over operations of a long-standing clients’ facility. While completing on-site background investigations on the treatment system, IFM discovered that there were a few deficiencies, one of them being a possible water logged bladder tank...